creating a filtered list of tasks across multiple projects

C

Chris_J_S

I'm still a bit new to MS-Project Server, but I got to believe that there is
a way to create a filtered list of tasks across all of our schedules that can
be shown in PWA. I'm sure that we will get more creative as time goes by,
but for now I will be happy with a list of tasks that have a certain flag set
to "yes". I want to see all of the tasks that meet that criterion, no matter
what file has them. Suggestions?
 
B

Ben Howard

Hi Chris,

Create a view in the MSP_PORTFOLIO cube, that filters/lists by tasks by your
task enterprise field. You'll need to add the enterprise fields into the
cubes (cube configuration) before you build it.
 