Creating a Fiscal Month Calendar ?

D

dan

I am curious if there is a way to change the days
associated with a month in MS Project to match my
Companies Fiscal Calendar.

For Example,
Project Displays the Month of April as April 1 - 30.
My Companies Fiscal Month April Starts on March 29 and
goes through April 25th.

I have not read anything suggesting that this is
possible. Just thought some of you may be having a
similar problem.
 
J

John

Dan,
A fiscal month option is not available with any version of Project.
However using VBA it is possible to develop custom data (e.g. cost,
headcount, EV, etc.) based on a company's financial calendar. I have
done this a couple of times and it works very well. I basically used the
Project calendar based data, converted it to company financial calendar
data and exported the results to an Excel spreadsheet.

John
 