A
Andrew
I am trying to create a bar to represent planned progress ie how much of the
duration should have been done to the status date. I have the planned % via a
macro as a number and I thought I could get the planned duration by
pln%/100xbaseline duration and drop the days into a duration1 field - seems
to work. the problem I have is when I try to creat a finish to put it in the
bar format section via baseline start + Duration1 dropping it into Finish1
the date is out by literally years. What am I doing wrong?
Andrew
duration should have been done to the status date. I have the planned % via a
macro as a number and I thought I could get the planned duration by
pln%/100xbaseline duration and drop the days into a duration1 field - seems
to work. the problem I have is when I try to creat a finish to put it in the
bar format section via baseline start + Duration1 dropping it into Finish1
the date is out by literally years. What am I doing wrong?
Andrew