Creating a new project using PSI (Project Server 2007)

R

Rob 19

I have been tasked with programmatically creating a new project in Project
Server 2007 with information taken from a seperate in-house application. The
information will include: tasks, effort, resourse assignments, and project
manager.

My first thoughts are to
-create a new project from an Enterprise Template in project server, as all
the projects will be of the same structure.
-delete the not needed tasks fro mthe created project.
-create an project resource pool from the info provided (all resources will
be available in the enterprise resource pool).
-add effort to the remaining tasks.
-assign resources to the appropriate tasks.
-assign a project manager and status manager.

My question is all this possible through PSI? My main concerns are around
the area of creating the project resource pool and assigning resources to the
tasks, and assigning effort.

Also is this the best approach?

Any help would be appreciated.

Thanks,

Rob.
 
D

Dale Howard [MVP]

Rob --

I would recommend you post this question in the
microsoft.public.project.developer newsgroup, as you are more likely to get
a reply there. Hope this helps.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top