Creating a Report for a certain Resource and a certain Date

A

Adrian

I have to create a report that shows how many hours of work a certain
resource should spend on some tasks on a certain date.

An example would be a report for Resource X on December 20th.
There should be a list of tasks showing a certain amount of hours for each
task,
e.g.

Task A - 2 hours
Task B - 4 hours
Task C - 2 hours

In a crosstab report I use a filter to get the tasks that are scheduled for
that date.
Every row is a task, the columns are days.

But then the report gives me 88 columns dislaying every single day of the
project.
I want this report to display only the assigned hours for that day.

I'd be happy about any suggestions on that.

Thanks,
Adrian
 
J

JulieS

Adrian,

You can select specific dates ranges to print in the Print command.
Preview your report to make sure you have the information you need
and then in the Print command, set the date range needed.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
 
A

Adrian

Thank you JulieS, that solves my issue.
I just haven't checked the print settings for a date range selection...

Adrian
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top