Creating a shift work calendars

  • Thread starter Tony Shoebridge
  • Start date
T

Tony Shoebridge

Attempting to setup a shift calendar that starts at 7pm
and finishes at 7am the following day. MSP doesnt accept
the start date cause it thinks it is later than the
finish.

Any suggestions.
 
D

DDM

Tony, assume M-F 7PM-7AM no break (for simplicity's sake):

Monday: From 7pm, To 12am.
Tues-Fri: From 12am, To 7am; From 7pm, To 12am.
Sat: From 12am, To 7am.

Note:

Mon only shows the hours actually worked on Mon (7pm-12am).
Tues-Fri have two From entries (12am, 7pm) and two To entries (7am, 12am).
Sat shows the hours left over from Fri (12am-7am).
 
M

Mike Glen

Hi Tony,

Welcome to this Microsoft Project newsgroup :)

You might like to have a look at my series of Microsoft Project lessons in
the TechTrax ezine, particularly Lesson 12 - Working Pattern, at this site:
http://tinyurl.com/2xbhc (Perhaps you'd care to rate it before leaving the
site, :) Thanks.)

FAQs, companion products and other useful Project information can be seen at
this web address: <http://www.mvps.org/project/>

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
 