Hello texmaster,
For clarification, it appears as though you want to compare the
Baseline Finish to the current date -- if the Baseline finish
is
greater than 5 days away it's green. If the Baseline Finish is
less than 5 days away, yellow, if the Baseline finish is
earlier
than today, red, and if the task is finished, blue.
So, to get you started. In a spare text field create the
following formula
IIf([% Complete]=100,"Complete",IIf([Baseline
Finish]=ProjDateValue("NA"),"No
Baseline",IIf(DateDiff("d",[Current Date],[Baseline
Finish])>=5,"Green",IIf(DateDiff("d",[Current Date],[Baseline
Finish])>=0,"Yellow","Red"))))
I hope this helps. Let us know how you get along.
Julie
Project MVP
Visit
http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
Hi Jonathan,
For now, I'm comparing it the current date whatever that is
when
its
opened. My group is new to project and they want the ability
to
open a
project, look at the current date structure and basically,
look
for
yellow and pay attention to those tasks.
I'm sorry to say for a group of 8 guys, we have over 35 active
projects
and I can't get management to purchase project server this
year.
For example,
Many of my projects for now have task name, duration, start
finish and
predecessors along with percentage complete and thats it.
I would like to move to what you are proposing having a finish
date and
actual finish date to compare when tasks are actually
completed.
Sorry if I'm being cryptic.
Thanks for any help you can provide.
'Jonathan Sofer [MVP Wrote:
;4645938']What are you using to compare to the finish date?
Are
you
comparing Finish
to Baseline Finish or are you comparing where the actual has
currently
been
progressed to i.e. [Stop] and comparing that to your
[Finish]?
I think I can provide you with a formula and instructions if
you
can
clarify
this point.
Jonathan
Hi,
Not really new to project but custom fields absolutely.
For
most
projects, I keep it simple with Start, Finish, Hours etc.
What I really need is a field I'm guessing formula that
will
act as
a
traffic stop light depending on how close or over a task is
from the
"Finish" field for example.
Ie for green, that would be for tasks 5 days or more away
from
the
finish date
for yellow, under 5 days from finish
for red, over the finish date
and blue for completed tasks.
--
texmaster
------------------------------------------------------------------------
texmaster's Profile:
http://forums.techarena.in/members/142408.htm
View this thread:
http://forums.techarena.in/microsoft-project/1256767.htm
http://forums.techarena.in
--
texmaster
------------------------------------------------------------------------
texmaster's Profile:
http://forums.techarena.in/members/142408.htm
View this thread:
http://forums.techarena.in/microsoft-project/1256767.htm
http://forums.techarena.in