Hi
1). What is the usage of Creating Cross-Project Links ?
As I understand, "Cross-project links are useful when two or more projects
have only a few tasks that affect one another. For example, a milestone
within a development project might trigger a task in an advertising campaign
project."
2). How it is implemented in Project 2007 ?
When I copied the task from the source project into my project ( target
project ) using "Paste Special", the new task I created become another task
in my target project. My observation is both task ( ie. task in the source
and task in the target ) behaving very independently as if they don't have
any link.
Here is my questions.
a) Obviously they are linked.
How the schedule and cost changes in the source projects is getting
reflected in target project. vice versa.
Like I said, my observation is they are behaving like independent task
although they are same task.
3). What is the difference between the "Paste Special" and "Past as
Hyperlink" ?
thanks
KS
1). What is the usage of Creating Cross-Project Links ?
As I understand, "Cross-project links are useful when two or more projects
have only a few tasks that affect one another. For example, a milestone
within a development project might trigger a task in an advertising campaign
project."
2). How it is implemented in Project 2007 ?
When I copied the task from the source project into my project ( target
project ) using "Paste Special", the new task I created become another task
in my target project. My observation is both task ( ie. task in the source
and task in the target ) behaving very independently as if they don't have
any link.
Here is my questions.
a) Obviously they are linked.
How the schedule and cost changes in the source projects is getting
reflected in target project. vice versa.
Like I said, my observation is they are behaving like independent task
although they are same task.
3). What is the difference between the "Paste Special" and "Past as
Hyperlink" ?
thanks