I have created a new project plan with a calendar for my company.
Now I wish to publish the project plan.
I have copied the calendar using organiser in the Checked out Enterprise
Global.
When I save the project plan, in the calendar column I get only the Standard
calendar displayed.
While saving the proejct plan to Enterprise, I get an error saying "Invalid
Base Calendar".
How do I copy my company's base calendar into the Enterprise.

Regards
Meena
 
D

Dale Howard [MVP]

Meena --

I already answered your queston once. You need to create the calendar in
the Enterprise Global file and not in the projects individually. Hope this
helps.
 