H
higginffx
I tried to create a new calendar in the Enterprise Global by both copying an
existing calendar and creating a new base calendar. Both times, I was
allowed to create and edit the working time in the new calendar (called
Calendar 1), but when I tried to rename it by opening
Tools>Organizer>Calendars, I got a message that "Base calendars cannot be
added to this project, check out the enterprise global to add or edit base
enterprise calendars". But that's what I had done to create Calendar 1 in
the first place. What am I doing wrong?