When I create a new project using a template I've set up (or saving from an
existing project), I notice that the MSP_WEB_ASSIGNMENTS table is not
populated with the existing assignments from the template. Doing a publish
all info does not populate it. Only doing a republish assignments will fill
the table with the expected assignments.

Question is, why does the publish all info not work?
 
B

Boris Key

Hi Rob,

I had the same issue. But probably it is feature ;) If you wait for couple
of days, actual time will be populated on server in MSP_WEB_ASSIGNMENTS
table. At least it works so for server in my company
 