I'm trying to create a relative time constraint in project, but I can'
seem to find any option other than entering a fixed date. Exampl
below.
I want task 2 to start no earlier than two weeks after task
completes, and I want task 2 to complete no earlier than four week
after task 1 completes. I don't want to enter the actual value of ([tas
1 complete date]+[2 weeks]) for my start date, because task 1 will hav
an end date that is variable.
Can anyone tell me how I could get Project (2007) to accept a formul
for the date restrictions?
Thanks in advance
seem to find any option other than entering a fixed date. Exampl
below.
I want task 2 to start no earlier than two weeks after task
completes, and I want task 2 to complete no earlier than four week
after task 1 completes. I don't want to enter the actual value of ([tas
1 complete date]+[2 weeks]) for my start date, because task 1 will hav
an end date that is variable.
Can anyone tell me how I could get Project (2007) to accept a formul
for the date restrictions?
Thanks in advance