We tried all but failed so far:
We want to create tasks by macro where we control which Unique ID or GUID the task should get. This we have simple connector to our software.
Is that possible to control this at creation via VBA macro? Current we store our UID in a text field and need to do lot to maintain this(e.g. Identify copies ...).
Primavera allows this in a simple way. MS Project seems to be harder here.