C
Craig Smillie
Hi,
I'm trying to create 4 tasks that all have to finish by 30 September and
start today. Howeve the actual work of each task is only about 3 days per
task, and they're not dependent on each other to finish.
My trouble is when I what I'd liek to show is the the duration of each
task as 3 days, with a start date of today and a complete date of 30 Sep,
then have the team members just update the % Work compelted.
When I try to do it, Project 2007 always adjusts the Start and End date to
be the duration, not the actual work involved.
Hope this makes sense, any help appreciated
Thanks
I'm trying to create 4 tasks that all have to finish by 30 September and
start today. Howeve the actual work of each task is only about 3 days per
task, and they're not dependent on each other to finish.
My trouble is when I what I'd liek to show is the the duration of each
task as 3 days, with a start date of today and a complete date of 30 Sep,
then have the team members just update the % Work compelted.
When I try to do it, Project 2007 always adjusts the Start and End date to
be the duration, not the actual work involved.
Hope this makes sense, any help appreciated
Thanks