Hello,
We are running Project Server 2003 with PWA. We are trying to create a
new project View in PWA that wil allow us to see tasks with a certain date
and % level. We setup the view and the filters that say show tasks that have
a % complete of less then or equal to 99% and a Start less then or equal to
10/5/2007. When we use the view on the project in displays nothing and greys
out the view drop down list.
If I change the date to any other date outside of October (10) the view
works fine, it only has an issue with the month of october (which happens to
be the current month). Is this normal for PWA or is this a bug, and does
anyone know a way to fix this.
Any Help would be greatly appreciated. Thank you in advance
We are running Project Server 2003 with PWA. We are trying to create a
new project View in PWA that wil allow us to see tasks with a certain date
and % level. We setup the view and the filters that say show tasks that have
a % complete of less then or equal to 99% and a Start less then or equal to
10/5/2007. When we use the view on the project in displays nothing and greys
out the view drop down list.
If I change the date to any other date outside of October (10) the view
works fine, it only has an issue with the month of october (which happens to
be the current month). Is this normal for PWA or is this a bug, and does
anyone know a way to fix this.
Any Help would be greatly appreciated. Thank you in advance