K
Katie B
Greetings,
In doing some investigation in Project Professional, I've discovered
how to create new Published Fields in the Enterprise Global and how to
create formulas, but for some reason, the new formula that I created
for a modified Remaining Work is calculating the wrong end results that
I'm looking for. Is there an easier way to simply modify the current
Remaining Work field, so that instead of calculating "Work - Actual
Work," it calculates "Baseline Work - Actual Work?" All tasks in our
project are Fixed Work and are calculated in (hrs). I unfortunately
did not originally create our work plan, and the creators are no longer
on this project to refer to for questions, which has made this kind of
a challenge.
Any clues as to how this is done? And please let me know if you need
more information than what I've provided.
Also, I was browsing in the Customize Enterprise Fields (which are also
Published fields) within the Enterprise Global to locate the fields
that we publish, such as Start Date, End Date, Baseline Work, Actual
Work and Remaining Work, etc, and I cannot seem to find them to make
modifications. I've tried checking all radio buttons relating to
Fields: Task, Resource and Project and I've tried all selections from
the Type: DropDown box from Cost to Text and cannot locate any of the
fields. Am I looking in the wrong spot for these?
Any advice you could pass along would be greatly appreciated.
Thanks!
Katie Begell
In doing some investigation in Project Professional, I've discovered
how to create new Published Fields in the Enterprise Global and how to
create formulas, but for some reason, the new formula that I created
for a modified Remaining Work is calculating the wrong end results that
I'm looking for. Is there an easier way to simply modify the current
Remaining Work field, so that instead of calculating "Work - Actual
Work," it calculates "Baseline Work - Actual Work?" All tasks in our
project are Fixed Work and are calculated in (hrs). I unfortunately
did not originally create our work plan, and the creators are no longer
on this project to refer to for questions, which has made this kind of
a challenge.
Any clues as to how this is done? And please let me know if you need
more information than what I've provided.
Also, I was browsing in the Customize Enterprise Fields (which are also
Published fields) within the Enterprise Global to locate the fields
that we publish, such as Start Date, End Date, Baseline Work, Actual
Work and Remaining Work, etc, and I cannot seem to find them to make
modifications. I've tried checking all radio buttons relating to
Fields: Task, Resource and Project and I've tried all selections from
the Type: DropDown box from Cost to Text and cannot locate any of the
fields. Am I looking in the wrong spot for these?
Any advice you could pass along would be greatly appreciated.
Thanks!
Katie Begell