I don't recommend this, but you can set a task constraint to "Must Start
On," "Must Finish On," or any number of other constraints and the "Critical"
flag will be set.
From your question, I'm guessing that you are trying to say that the task is
"really important" hence the "Critical" label. However in project management
lingo, "Critical" has a specific meaning - one way to thinkof it this...-
any task that is "Critical" is part of the sequence of tasks that define the
total duration of the project and if any of these tasks change duration,
start date, or end date the projectED end date of the project will change
Perhaps you are wondering why the "Must start on" and "Must finish on"
settings matter. - Dale's post above mentions "Float", the MSO and MFO
flags, in effect, zero out the float. Zero float means "Critical"
Hope that helps more than it confuses...
Mark
--
_________________________________________________________
Mark Durrenberger, PMP
Principal, Oak Associates, Inc,
www.oakinc.com
"Advancing the Theory and Practice of Project Management"
________________________________________________________
The nicest thing about NOT planning is that failure
comes as a complete surprise and is not preceded by
a period of worry and depression.
- Sir John Harvey-Jones