D
daniel smatt
Hi Guys
I need an answer to a Question that someone asked me at an interview
I have a task that has 100days duration. when i filter for tasks on
the
Critical path this particular task shows up on the critical path.
The
reason why the task is 100days is because it's some thing that's
repetitive on a weekly basis and i don't want to break teh Task into
Sub Task
How can i ensure that this Task is not reflected as been critical when
i filter on activities on the critical
path.
I need an answer to a Question that someone asked me at an interview
I have a task that has 100days duration. when i filter for tasks on
the
Critical path this particular task shows up on the critical path.
The
reason why the task is 100days is because it's some thing that's
repetitive on a weekly basis and i don't want to break teh Task into
Sub Task
How can i ensure that this Task is not reflected as been critical when
i filter on activities on the critical
path.