Critical Path Errors

J

Janbird

I'm copying schedules from one file and pasting to another-
-I'm getting basically "red" schedules. Do I actually
have to build each schedule separately, or is there a
better way to do this? How do I make the schedules which
are not really containing a critical path "normal," now
that I've done this. Thanks!!
 
J

Jan De Messemaeker

Hi Janbird,

Tasks in a schedule are critical when they do not have slack.
Critical or not is calculated by Project.
The method to calculate slack is not specific to Project, it has been
developped more than half a century ago.
Read all about it in http://www.mvps.org/project/faqs.htm
Faq 42. A guide to Network Analysis.

HTH
 