Critical Path belongs to the Project, not to a specific milestone. So, there
really isn't such thing as a critical path to a milestone. If you create a
separate file with all the predecessors to that milestone (and only those
predecessors), then you could show that critical path.
In the meantime, there are two options that come to mind for use in the
existing file. The hard one first.
One of the MVPs, Jack Dahlgren, created a Macro that will identify a trace
of all the predecessors (or successors) to a specific task. I believe it
sets the Flag5 field to "yes" for the items of interest.
Here is a link to that macro:
http://masamiki.com/docs/trace-task-dependencies.html
That will give you the opportunity to show only the predecessors to that
task, or even only those predecessors that are on the project critical path.
This could also be filtered for Critical Path, and displayed as a network
diagram.
Another way -- There is a companion software product called "PERT Chart
Expert" put out by Critical Tools.
http://www.criticaltools.com It installs
itself and a toolbar to MS Project. I think they have a free trial. More
info on the link below my name -- select companion products.
If you highlight the milestone, jump to PERT Chart Expert, you are two mouse
clicks from a graphical representation (network diagram). We print it as a
PDF and send it off to our customer.
--
If this post was helpful, please consider rating it.
Jim
It''s software; it''s not allowed to win.
Visit
http://project.mvps.org/ for FAQs and more information
about Microsoft Project