Critical Path in large project.

K

KZH

Good day, I have a large project but need the critical path for only the
first phase which is about a year in length. How do I break the master
project so I can develop the critical path.
 
R

Rob Schneider

KZH said:
Good day, I have a large project but need the critical path for only the
first phase which is about a year in length. How do I break the master
project so I can develop the critical path.

Separate the large project into separate subproject files. Then open
each subproject file independently to show its own critical path. You
can join the multiple projects into a master project. See master and
subproject files in the "help" file for more info.
 