D
Dave N
Hi everyone.
I'm relatively new to using MSP in anger and I have a
major issue with the way it shows the critical path.
If all the tasks on the CP are dependencies of each other
then it's all fine and dandy with nice red tasks to
highlight the CP.
If however you assign no dependencies but have all tasks
assigned to the same resource, then it does not show
these as the CP.
Now my understanding of the definition of the CP is any
tasks that, if delayed, will cause a delay in the
earliest completion time of the project. By definition
if all tasks are assigned to a single resource then a
delay in any task will therefore cause a delay in the
project and so is critical!
Anyone got any thoughts on this as it's quite significant
if I can't easily identify the CP in a large schedule
(currently around 700 lines and growing.)
Dave.
I'm relatively new to using MSP in anger and I have a
major issue with the way it shows the critical path.
If all the tasks on the CP are dependencies of each other
then it's all fine and dandy with nice red tasks to
highlight the CP.
If however you assign no dependencies but have all tasks
assigned to the same resource, then it does not show
these as the CP.
Now my understanding of the definition of the CP is any
tasks that, if delayed, will cause a delay in the
earliest completion time of the project. By definition
if all tasks are assigned to a single resource then a
delay in any task will therefore cause a delay in the
project and so is critical!
Anyone got any thoughts on this as it's quite significant
if I can't easily identify the CP in a large schedule
(currently around 700 lines and growing.)
Dave.