A
Ange
Hi
Is there any way you can define the critical path in project ie. can you
tell project which task you want it to calculate the critical path from. I am
working on a large project and have tasks in our schedule that are continuing
post Go Live but want to be able to see the critical path to our Go Live
date. Currently, I am only able to see the critical path to the last date in
the schedule (which is 1 year post our Go Live date).
Thanks
Ange
Is there any way you can define the critical path in project ie. can you
tell project which task you want it to calculate the critical path from. I am
working on a large project and have tasks in our schedule that are continuing
post Go Live but want to be able to see the critical path to our Go Live
date. Currently, I am only able to see the critical path to the last date in
the schedule (which is 1 year post our Go Live date).
Thanks
Ange