B
Bud
Hello,
I set up a schedule with 4 Non direct tasks such as Business Analyst
oversight, manage project, etc. I set these up as fixed duration and I do
want them to run the length of the project which is one year. I have them
finishing slightly shorter than the end of the project but that still doesn't
make any difference.
These are masking the true critical path of the project as they have 0 total
slack and are flagged as critical.
I can set the multiple path on and than it will show several critical paths.
However, I would like to know what the true main critical path is.
How can I do this?
Thanks
I set up a schedule with 4 Non direct tasks such as Business Analyst
oversight, manage project, etc. I set these up as fixed duration and I do
want them to run the length of the project which is one year. I have them
finishing slightly shorter than the end of the project but that still doesn't
make any difference.
These are masking the true critical path of the project as they have 0 total
slack and are flagged as critical.
I can set the multiple path on and than it will show several critical paths.
However, I would like to know what the true main critical path is.
How can I do this?
Thanks