N
neverland
My project file is too large and complex(Team members:50,
duration:12 month).Are there some tips to make the project
plan,to set the dependence between the tasks,so I can get
the critical path?
My project is a telecom exchange device R&D project ,it
has requirement analysis/high level dev/low level
dev/testing etc. phases..
thanks
duration:12 month).Are there some tips to make the project
plan,to set the dependence between the tasks,so I can get
the critical path?
My project is a telecom exchange device R&D project ,it
has requirement analysis/high level dev/low level
dev/testing etc. phases..
thanks