Greg --
If this is your first project, I think you did exceptionally well. There
were several things I liked about your project:
1. I could see a series of "waterfalls" running through your project,
indicating that you sequenced your tasks in the order in which they occur.
2. You made effective use of summary tasks to show Phase and Deliverable
sections in the project.
3. You used Milestone tasks to signify the completion of each Phase and/or
Deliverable section.
4. You did not link summary tasks to anything else. That helps to minimize
the risk of a circular reference error.
5. You linked regular tasks to each other and to Milestone tasks.
6. You added Notes to tasks to provide additional documentation on those
tasks.
7. You added nonworking time to the personal calendar of one resource in
the project.
8. You baselined your project.
Whoever taught you to use Microsoft Project has taught you well! And if you
taught yourself, congrats! Since you asked, there are several changes I
would recommend:
1. Your project is missing the Project Summary Task (Row 0 or Task 0). To
display it, click Tools - Options - View and select the "Show project
summary task" option.
2. You have several "dangling" tasks in your project, which are tasks with
no Predecessor and/or Successor. These tasks lead nowhere in the project
and I would recommend you link them to something.
3. You have a number of serious resource overallocations in your project,
in the range of 16 or more hours per day. These overallocations are serious
enough to cause your project to slip. I would recommend that you level your
project in some manner to resolve the overallocations that are greater than
8 hours per day.
4. Your project is already showing variance, even though the project has
not been updated with progress from the first week. To see the variance,
apply the Gantt Chart view and then click View - Table - Work or View -
Table - Variance. Examine the Work Variance column and the Finish Variance
column in their respective Tables. At this point in the life of the
project, there should be NO variance. I suspect you baselined the project
before you were finished planning the project, or only baselined part of the
project. I believe you should baseline the entire project before you begin
entering progress in the plan.
Hope this helps.