critical path questions

J

Joy

is it possible that a project has no critical path?

my macros can show critical path. the filter critical can show only critical
tasks. the issue is in Gantt Chart, the bar is blue instead of red. can I
change it by vba codes? I know how I can do it manually in ms project.
 
J

Jack Dahlgren

If you can change it manually, you can almost always do it in code. The easy
way to figure it out is to turn on the macro recorder, do the actions you
want. Turn off the recorder and then review the code that was produced.

In this case, you need to look at formatting menu / barstyles to get the
critical tasks to show up as red.

-Jack
 
J

Joy

ok, got it
I tried to record one earlier, but I am a little bit confused, and I thought
I could not make it by recording.

then I look closely, and find a way

thank you!
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top