A
andy
Hi hope someone can help,
when using the gantt view "entry" - it is possible to pull up a task form
view where you are able to select resources/predecessors, etc,
when using this task form to display predecessors, / successors is there a
way that i can show the % c/t bar as well - this would allow me to see not
only the tasks but the status of each predecessor as some of my projects have
more than one dependancy and without viewing each of them you cannot
determine where the delay is
thanks in anticipation
when using the gantt view "entry" - it is possible to pull up a task form
view where you are able to select resources/predecessors, etc,
when using this task form to display predecessors, / successors is there a
way that i can show the % c/t bar as well - this would allow me to see not
only the tasks but the status of each predecessor as some of my projects have
more than one dependancy and without viewing each of them you cannot
determine where the delay is
thanks in anticipation