Hi,
I am currently busy buidling a relatively large and long a project which
makes it difficult to view the whole project on the PC screen. If I change
the view to show the critical path, only the bars in the Gantt chart change
to red. I would appreciate it if someone could help me to change the colour
of the tasks in the critical path as well (the wording in the task name
spreadsheet column), if this is possible. By having this, I would be able to
see which tasks is on the critical path by just looking at the list of tasks.
This is also very helpfull when you print the project.
Best Regards
Diederick
I am currently busy buidling a relatively large and long a project which
makes it difficult to view the whole project on the PC screen. If I change
the view to show the critical path, only the bars in the Gantt chart change
to red. I would appreciate it if someone could help me to change the colour
of the tasks in the critical path as well (the wording in the task name
spreadsheet column), if this is possible. By having this, I would be able to
see which tasks is on the critical path by just looking at the list of tasks.
This is also very helpfull when you print the project.
Best Regards
Diederick