critical path VS milestone

J

Jie

I am not sure whether MS Project can represent them (critical path VS milestone) both with associated deliverables

Does anybody know

Thanks in advance
 
W

William Raymond

Hello,

Actually, critical path and milestones are two very different things. If an
activity slips on the critical path, the entire project slips. A milestone
is just a way to highlight key areas in the project where certain important
deliverables are complete or nearing completion.

With Microsoft Project, the critical path is automatically calculated.
Milestones are represented by creating zero-day tasks (however, you can have
tasks with more than zero days and mark it as a milestone). You can tie
important deliverables to the milestone so it automatically adjusts to show
when the milestone will hit.... do this by using the predecessor/successor
links to tie the deliverables to their appropriate milestones.

Is this what you were looking for?


-Bill
--
Bill Raymond
projectnation at hotmail dot com


Jie said:
I am not sure whether MS Project can represent them (critical path VS
milestone) both with associated deliverables.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top