D
davekmd
Folks, the 'classical' training (and pm s/w) I've previously used eons ago
would not allow linking (or assigning) summary level tasks. I've broken with
tradition and have created a rather large network of some 480 tasks using 5
WBS levels. I've done linking of summary tasks to other summary tasks.
(seems like a wonderful feature).
Initially when I filtered for Critical Tasks all I got was about 12 tasks
out of my 480. The 1st critical task shown was an overall summary task at
the highest WBS level, but no subtasks were shown underneath of it. This was
followed by a lower WBS level subtask, but this showed the subtasks.
So it was kind like this ...
3 mega summary task (no subtasks shown under this mega summary task)
3.7 summary sub task
3.7.1 subtask a
3.7.2 subtask b
3.7.3 subtask c
....etc.
Basically the subtasks under "3" weren't displayed. Now I did a search and
found that I probably needed to set the calculation option for multiple
critical paths. I have a bunch of critical paths now, so I suppose that's a
good thing.
My questions are ...
1. Is that right? I needed to enable multiple critical paths?
2. Is there any practical way to verify that what's shown are in fact the
tasks on multiple critical paths?
3. Is there an easy way to get a simple count of the critical path tasks?
4. Are multiple critical path schedules common / rare?
5. Generally speaking what gives rise to multiple critical paths (i.e., from
a modeling perspective what conditions generaly cause this?)
6. Are there any cautions I need to be aware of when linking summary tasks
to other summary tasks? (I have to be honest, this is pretty darn cool). I
can have 20, 30, 40 tasks at varying WBS levels under a high level summary
task for example "Step 1 office move". Then for the next mega summary level,
I can just make the task "Step 1 office move" the predecessor (FS) to the
summary "Step 2 office move". Slick. Nothing under Step 2 office moves
starts until everything in Step 1 finishes out.
Thanks much folks!
would not allow linking (or assigning) summary level tasks. I've broken with
tradition and have created a rather large network of some 480 tasks using 5
WBS levels. I've done linking of summary tasks to other summary tasks.
(seems like a wonderful feature).
Initially when I filtered for Critical Tasks all I got was about 12 tasks
out of my 480. The 1st critical task shown was an overall summary task at
the highest WBS level, but no subtasks were shown underneath of it. This was
followed by a lower WBS level subtask, but this showed the subtasks.
So it was kind like this ...
3 mega summary task (no subtasks shown under this mega summary task)
3.7 summary sub task
3.7.1 subtask a
3.7.2 subtask b
3.7.3 subtask c
....etc.
Basically the subtasks under "3" weren't displayed. Now I did a search and
found that I probably needed to set the calculation option for multiple
critical paths. I have a bunch of critical paths now, so I suppose that's a
good thing.
My questions are ...
1. Is that right? I needed to enable multiple critical paths?
2. Is there any practical way to verify that what's shown are in fact the
tasks on multiple critical paths?
3. Is there an easy way to get a simple count of the critical path tasks?
4. Are multiple critical path schedules common / rare?
5. Generally speaking what gives rise to multiple critical paths (i.e., from
a modeling perspective what conditions generaly cause this?)
6. Are there any cautions I need to be aware of when linking summary tasks
to other summary tasks? (I have to be honest, this is pretty darn cool). I
can have 20, 30, 40 tasks at varying WBS levels under a high level summary
task for example "Step 1 office move". Then for the next mega summary level,
I can just make the task "Step 1 office move" the predecessor (FS) to the
summary "Step 2 office move". Slick. Nothing under Step 2 office moves
starts until everything in Step 1 finishes out.
Thanks much folks!