E
emq_33
In creating my schedule in MS Project (2007), I probably violated
about every rule there is for creating it the right way. Let's just
chalk it up to bad luck on a number of fronts!
So, the problem:
I am trying to identify the critical path in the schedule and the only
thing that currently shows as being on the critical path are three
tasks smack dab in the middle of the schedule. The tasks are
sequential with the first being a predecessor of the second, etc. The
first task is preceeded by a milestone event ("Initiate
Development"). This construct occurs a couple of places in my
schedule.
However, I do have a final event ("Final Delivery") which has multiple
predessesors. I would expect the critical path to end with this
milestone and be part of the highlighted path. The tasks which are
currently highlighted as being in the critical path are indirect
predecessors of the "Final Delivery" milestone.
Even using the Gantt Wizard to define the critical path does not help.
Now for some of the probable rule violations:
* When the schedule was originally built, it was laid out as tasks
with fixed start and end dates. Predecessors were defined. The tasks
have since been converted to fixed duration and "start as soon as
possible".
* There is no single milestone that defines the start of the schedule
(eg "Contract Award"). Instead there are key activities consisting of
related tasks that start with an "Initiate Development" type
milestone.
The upsides?
* I am the only one who uses the schedule, so there are no issues
with synching, servers, etc
* It's a "duration" and percent complete schedule, ie no resources,
etc. Probably pretty simple in the bigger picture
* Don't have to baseline
Since I am not sure if this is too little or too much information to
analyze this problem, I will stop here. If more information is
required, just let me know.
Any suggestions on how to highlight the ciritical path will be greatly
appreciated! Or if I am hopelessly hosed over, I would like to know
that too!
Thanks!
Don
about every rule there is for creating it the right way. Let's just
chalk it up to bad luck on a number of fronts!
So, the problem:
I am trying to identify the critical path in the schedule and the only
thing that currently shows as being on the critical path are three
tasks smack dab in the middle of the schedule. The tasks are
sequential with the first being a predecessor of the second, etc. The
first task is preceeded by a milestone event ("Initiate
Development"). This construct occurs a couple of places in my
schedule.
However, I do have a final event ("Final Delivery") which has multiple
predessesors. I would expect the critical path to end with this
milestone and be part of the highlighted path. The tasks which are
currently highlighted as being in the critical path are indirect
predecessors of the "Final Delivery" milestone.
Even using the Gantt Wizard to define the critical path does not help.
Now for some of the probable rule violations:
* When the schedule was originally built, it was laid out as tasks
with fixed start and end dates. Predecessors were defined. The tasks
have since been converted to fixed duration and "start as soon as
possible".
* There is no single milestone that defines the start of the schedule
(eg "Contract Award"). Instead there are key activities consisting of
related tasks that start with an "Initiate Development" type
milestone.
The upsides?
* I am the only one who uses the schedule, so there are no issues
with synching, servers, etc
* It's a "duration" and percent complete schedule, ie no resources,
etc. Probably pretty simple in the bigger picture
* Don't have to baseline
Since I am not sure if this is too little or too much information to
analyze this problem, I will stop here. If more information is
required, just let me know.
Any suggestions on how to highlight the ciritical path will be greatly
appreciated! Or if I am hopelessly hosed over, I would like to know
that too!
Thanks!
Don