V
Vincent Isoz
Hi,
Since MS Project exists the critical path calculation is incorrect as far as
i know (and it's not the only false point...).
If you have a task with a positive total slack and put him a constraint like
"must start on" she will become "critical" (red) but mathematically she's not!
I don't understand why this has not been corrected since this last 10 years
O_O
The computer scientist by Microsoft have to revised the Dijkra algorithm in
ponderated and connex graph theory to calculate correctly the critical path
as Primavera do.
When will this be corrected... in 2 years... or 10 years again? I lot of my
customers are unsatisfied by this behavior.
Thanks for your answer
Since MS Project exists the critical path calculation is incorrect as far as
i know (and it's not the only false point...).
If you have a task with a positive total slack and put him a constraint like
"must start on" she will become "critical" (red) but mathematically she's not!
I don't understand why this has not been corrected since this last 10 years
O_O
The computer scientist by Microsoft have to revised the Dijkra algorithm in
ponderated and connex graph theory to calculate correctly the critical path
as Primavera do.
When will this be corrected... in 2 years... or 10 years again? I lot of my
customers are unsatisfied by this behavior.
Thanks for your answer