Critical Path

D

daniel smatt

Hi Guys

Am i need an answer to a Question that some asked me
i have a task that is 100days duration. when i filter for tasks on the
Critical path this particular task shows up on the critical path. The
reason why the task is 100days is because it's some thing that's
repetitive on a weekly basis. How can i ensure that this Task is not
reflected as been critical when i filter on activities on the critical
path.
 
G

gugliupj

While everyone gave good answers... after doing this for more years than I
want to admit, and having been asked this question several times; because
some Cost Analyst has to lower the amount of LOE hrs and decided this had to
be a discreet task... shorten the task by 1 day and it will not show up on
the critical path.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top