Critical Path

K

KQ-at-Hub

I have a project of around 1500 activities, 'Critical' filter showing me
every activity or every activity has gone critical. Slack is set at less than
2 days and 'Multiple Critical Path' is unchecked.

Kashif Qamar
 
R

Rod Gill

So have you linked all tasks together with no (or minimal) dates entered?
Please explain how you built your Tasks and links etc.

--

Rod Gill
Microsoft MVP for Project

Author of the only book on Project VBA, see:
http://www.projectvbabook.com
 
M

Mike Glen

Hi Kashif,

Welcome to this Microsoft Project newsgroup :)

Set Project/Project Information... Schedule From: Project Start Date

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for Project Tutorials
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Similar Threads


Top