glenn
To format my bars throughout the schedule I select the Task Name column and
then I select Format | Bars from the main menu. I then click on the Text tab
and I select % Complete for left, Resource Name for top and Name for right.
My problem is that whenever a task becomes critical, it overwrites the
formatting I previously set leaving unreadable garbled text near the bar.
I am using MS Project 2002 Pro
What am I missing??
thanks