B
Bill Swihart
I can not get a task that has obvious slack to show up as non critical.
I have a task (T3) that is constrained to start no sooner than... and is
linked to a critical task (CT4). The critical task is driven by another
task (T2) that sets the start date of CT4 well beyond the finish date of
T3. T3 shows as critical. If I remove the constraint of T3 to ASAP then it
becomes non-critical but does not start when I need it to.
Moving it back causes it to show critical. Suggestions please.
Bill
I have a task (T3) that is constrained to start no sooner than... and is
linked to a critical task (CT4). The critical task is driven by another
task (T2) that sets the start date of CT4 well beyond the finish date of
T3. T3 shows as critical. If I remove the constraint of T3 to ASAP then it
becomes non-critical but does not start when I need it to.
Moving it back causes it to show critical. Suggestions please.
Bill