L
L8rdays
I hope you can tell me what I'm doing wrong, because I can't believe it works
this way.
Actually this question applys regardless of cross project or locally linked
tasks.
Task 3 % complete = 20 Linked to start after Task 2 has finished.
If Task 2 duration changes impacting the finish date and it is tied to
another task that has something other than 0% complete, it doesn't update
that task. In this case Task 3 wouldn't show a change because task 2 slipped.
Why??? I'm assuming there is logic behind this, I need help understanding
this and training it.
Thanks
this way.
Actually this question applys regardless of cross project or locally linked
tasks.
Task 3 % complete = 20 Linked to start after Task 2 has finished.
If Task 2 duration changes impacting the finish date and it is tied to
another task that has something other than 0% complete, it doesn't update
that task. In this case Task 3 wouldn't show a change because task 2 slipped.
Why??? I'm assuming there is logic behind this, I need help understanding
this and training it.
Thanks