T
Terry Peters
Good Day:
My client has used a master project to create cross-project dependency links
between two projects (saving changes to the linked projects but not saving
the master project to Project Server 2003). The external predecessor and
successor show up as expected in each project. However, they are just now
noticing that even when they have made no changes to their linked tasks, the
"Published New and Changed Assignments" indicator displays for the task,
prompting them to update the server. I have not been able to test this out
at their site yet due to my travel schedule, but am wondering if (a) this
simply is due to changes made in the other linked project (my supposition
currently), or (b) this is just a fluke in the way Project Server handles the
external links? Let me know please if you have encountered this phenomenon.
Thanks,
My client has used a master project to create cross-project dependency links
between two projects (saving changes to the linked projects but not saving
the master project to Project Server 2003). The external predecessor and
successor show up as expected in each project. However, they are just now
noticing that even when they have made no changes to their linked tasks, the
"Published New and Changed Assignments" indicator displays for the task,
prompting them to update the server. I have not been able to test this out
at their site yet due to my travel schedule, but am wondering if (a) this
simply is due to changes made in the other linked project (my supposition
currently), or (b) this is just a fluke in the way Project Server handles the
external links? Let me know please if you have encountered this phenomenon.
Thanks,