Crosstab reports

S

stephen

I am using the Resource Usage report, but the task
assignments are not displayed, despite the "And task
assignment" box is checked. I have also created a new
crosstab report with all the correct settings, but the
task assignments do not display. (Resource assignments
on Task Usage report do display however.)

Any suggestions?

Thanks
 
D

Dale Howard [MVP]

Stephen --

Open the project plan, then apply the Resource Usage view. On the left end
of the Formatting toolbar, click the Show button and then select All
Subtasks. When you run the Resource Usage report, all of the task
assignments should now show. Hope this helps.
 