E
Ernie Longino
We are currently running Project Server 2003 SP2a with SQL Server 2000 in a
clustered environment.
The issue we are experiencing concerns actual hours from a specific project
that are not loading to the OLAP cube from the database. I know that this
can occur if a project is in a checked out state at the time the cube is
built, but I have verified that the project in question, as well as the
resources, were checked in before the cube build began. I have also verified
that the cube build completed successfully and that the date ranges for which
the cube is configured is adequate.
Does anyone here have experience with this or a similar issue?
Any help offered is greatly appreciated.
Ernie
clustered environment.
The issue we are experiencing concerns actual hours from a specific project
that are not loading to the OLAP cube from the database. I know that this
can occur if a project is in a checked out state at the time the cube is
built, but I have verified that the project in question, as well as the
resources, were checked in before the cube build began. I have also verified
that the cube build completed successfully and that the date ranges for which
the cube is configured is adequate.
Does anyone here have experience with this or a similar issue?
Any help offered is greatly appreciated.
Ernie