Cube Actuals do not match DB

E

Ernie Longino

We are currently running Project Server 2003 SP2a with SQL Server 2000 in a
clustered environment.

The issue we are experiencing concerns actual hours from a specific project
that are not loading to the OLAP cube from the database. I know that this
can occur if a project is in a checked out state at the time the cube is
built, but I have verified that the project in question, as well as the
resources, were checked in before the cube build began. I have also verified
that the cube build completed successfully and that the date ranges for which
the cube is configured is adequate.

Does anyone here have experience with this or a similar issue?

Any help offered is greatly appreciated.

Ernie
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top