S
Stex
I want to create a cube that will show an evaluation of “out of projectâ€
actual work hours.
For this I created a Custom Field in the Resource to contain the
[Estimation] in % that is to be used.
I created a second field in Resource to contain the following formula:
[Actual Hour] * [Estimation] / 60
Example: If we estimate that a resource is working 10% of is time out of
projects and the resource worked 125 hours, the expected result is 12.5 hours.
The result is what I expect in MS Project – Resource View
How can I obtain now to obtain a view that will show me the same but
including all the projects at the Project Server level?
Every suggestions are welcome.
actual work hours.
For this I created a Custom Field in the Resource to contain the
[Estimation] in % that is to be used.
I created a second field in Resource to contain the following formula:
[Actual Hour] * [Estimation] / 60
Example: If we estimate that a resource is working 10% of is time out of
projects and the resource worked 125 hours, the expected result is 12.5 hours.
The result is what I expect in MS Project – Resource View
How can I obtain now to obtain a view that will show me the same but
including all the projects at the Project Server level?
Every suggestions are welcome.