Cube Data Missing

W

Wendy

All,

For Project Server 2003, our cube has been consistently building
without issue; however, beginning this week, there is data not showing
in reporting. Specifically, in the MSP_Portfolio_Analyzer and
MSP_Assn_Fact cubes, none of the measures are displaying, although the
projects (and project and task-level attributes) do display. Through
MS Project at least, the projects do not appear problematic.

Does anyone have suggestions as to how/why this would occur and what
to review for troubleshooting?

Thank you,
Wendy
 
W

Wendy

All,

For Project Server 2003, our cube has been consistently building
without issue; however, beginning this week, there is data not showing
in reporting. Specifically, in the MSP_Portfolio_Analyzer and
MSP_Assn_Fact cubes, none of the measures are displaying, although the
projects (and project and task-level attributes) do display. Through
MS Project at least, the projects do not appear problematic.

Does anyone have suggestions as to how/why this would occur and what
to review for troubleshooting?

Thank you,
Wendy

To clarify, the measures are not showing for only SOME projects, not
all.
 