Cube data not showing correct actual costs for cost type resources

C

Caroline

Hi,
I'm trying to automate the collection of data about actual costs used
by our cost type resources. These are external contractors that are
shown in the project schedule with a milestone for each invoice. The
milestone has an actual cost against that resource.
When I try to create a report from Data Analysis the actual cost data
is simply wrong for cost resources, for normal resources it looks
fine.
Is this a known issue?
We are using Project Server 2007 and have recently applied service
pack 2.

Caroline
 
W

Wharton Computer Consulting

Make sure that your projects are being published and also that the cube is
being updated.
 
C

Caroline

Make sure that your projects are being published and also that the cube is
being updated.

--
Michael Wharton, MBA, PMP, MCSD, MCSE+I, MCDBA
Wharton Computer Consulting, Inc
"Managing Efficiency thru Technology"






- Show quoted text -

Yes thanks, both of those are happening. That's not the problem.

Any other ideas?

The values in the project centre views are correct and include all
costs, but I want to break it down by cost resource which I don't
think I can do in a project centre view, only in the cube data.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top