C
Caroline
Hi,
I'm trying to automate the collection of data about actual costs used
by our cost type resources. These are external contractors that are
shown in the project schedule with a milestone for each invoice. The
milestone has an actual cost against that resource.
When I try to create a report from Data Analysis the actual cost data
is simply wrong for cost resources, for normal resources it looks
fine.
Is this a known issue?
We are using Project Server 2007 and have recently applied service
pack 2.
Caroline
I'm trying to automate the collection of data about actual costs used
by our cost type resources. These are external contractors that are
shown in the project schedule with a milestone for each invoice. The
milestone has an actual cost against that resource.
When I try to create a report from Data Analysis the actual cost data
is simply wrong for cost resources, for normal resources it looks
fine.
Is this a known issue?
We are using Project Server 2007 and have recently applied service
pack 2.
Caroline