I have a problem with Cube build. I am the administrator (and PM) of many
projects created in MS-EPM server. Members submit their time and I accept
them and then at the end of week, I build the cube. Things were pretty fine;
that is, time shown against each tasks for any resource was rightly reflected
in the Portfolio analyzer outputs. One project, since last 2 weeks, is
continuously showing wrong time (rather Zeroes) aginst most of the tasks for
all the resources. I analyzed and compared time data from Project Pro 2003's
eResource view and Portfolio analyzer and found 2 weeks back result was
mostly same, but now all are mismatching. As if it detoriated as time passed
by. This is happening in just one project, while all other projects are okay.
By the way, these projects are open-ended ones. that means, end dates are not
declared (or I don't care). Also all tasks are "Fixed Units". I can supply
more information, if required. Please help me to understand what's happening.
Thanks in advance.
I have a problem with Cube build. I am the administrator (and PM) of many
projects created in MS-EPM server. Members submit their time and I accept
them and then at the end of week, I build the cube. Things were pretty fine;
that is, time shown against each tasks for any resource was rightly reflected
in the Portfolio analyzer outputs. One project, since last 2 weeks, is
continuously showing wrong time (rather Zeroes) aginst most of the tasks for
all the resources. I analyzed and compared time data from Project Pro 2003's
eResource view and Portfolio analyzer and found 2 weeks back result was
mostly same, but now all are mismatching. As if it detoriated as time passed
by. This is happening in just one project, while all other projects are okay.
By the way, these projects are open-ended ones. that means, end dates are not
declared (or I don't care). Also all tasks are "Fixed Units". I can supply
more information, if required. Please help me to understand what's happening.