D
Dredman
In October of 2005, a user named Haris posted the question below. He received
a workable answer, but it was not straightforeward. My question is, is there
a straightforeward way to view curent baseline in Project 2007 without
creative manipulation?
Don
----------Haris's question----------
Hi,
I'm trying to create a Project view in order to support Project Monitoring
for PMs. I need to show actuals and the baselines for the project. There are
11 fields for Baseline, how do i set up the view so that the recent baseline
is displayed in the view? (if possible) or do i have to update the view
everytime a new baseline is created? If so, any work arounds?
Looking forward to some help.
Regards,
Haris
a workable answer, but it was not straightforeward. My question is, is there
a straightforeward way to view curent baseline in Project 2007 without
creative manipulation?
Don
----------Haris's question----------
Hi,
I'm trying to create a Project view in order to support Project Monitoring
for PMs. I need to show actuals and the baselines for the project. There are
11 fields for Baseline, how do i set up the view so that the recent baseline
is displayed in the view? (if possible) or do i have to update the view
everytime a new baseline is created? If so, any work arounds?
Looking forward to some help.
Regards,
Haris