I have a Proj2K file in which the current date (10/27/03) line is
displaying in the first quarter of 04. The computer's system date is
correct, and Project's Project Information dialog is displaying the
correct date.

Does anybody know why Project's current date might be out of sync with
the actual date?

Thanks
Dave
 
J

Jack D.

Dave said:
I have a Proj2K file in which the current date (10/27/03) line is
displaying in the first quarter of 04. The computer's system date is
correct, and Project's Project Information dialog is displaying the
correct date.

Does anybody know why Project's current date might be out of sync with
the actual date?

Thanks
Dave

Double click on the timescale and make sure that the "use fiscal year" box
is NOT checked. That may have an effect.

--
Please try to keep replies in this group. I do check e-mail, but only
infrequently. For Macros and other things check http://masamiki.com/project

-Jack Dahlgren, Project MVP


+++++++++++++++++++
 