Current Progress in My Task

R

reza

Hi All,

In my task, if we click Import Timesheet, we will go to Import Timesheet
table, in that table there were Current Progress.....can we add that colom to
My Task. With that colom i can view how many work and total work that he/she
do [5h of 16h (31%).
anybody know how to add this colom to My Task view???

thanks in advance

reza
 
D

Dale Howard [MVP]

Reza --

The Project Server administrator can add the Actual Work column to the My
Assignments view (Server Settings - Manage Views). Hope this helps.
 
R

reza

Thanks dale, but this is not what i want...
in some article, i saw picture of My Task View, in that picture progress
column show data like this "5h of 16h (31%)". For more clearly you can click
import timesheet, in there you can see what i mean.

thanks

Dale Howard said:
Reza --

The Project Server administrator can add the Actual Work column to the My
Assignments view (Server Settings - Manage Views). Hope this helps.




reza said:
Hi All,

In my task, if we click Import Timesheet, we will go to Import Timesheet
table, in that table there were Current Progress.....can we add that colom
to
My Task. With that colom i can view how many work and total work that
he/she
do [5h of 16h (31%).
anybody know how to add this colom to My Task view???

thanks in advance

reza
 
D

Dale Howard [MVP]

Reza --

I'm not aware of any way to add what you want to see in the My Tasks page.
Hope this helps.




reza said:
Thanks dale, but this is not what i want...
in some article, i saw picture of My Task View, in that picture progress
column show data like this "5h of 16h (31%)". For more clearly you can
click
import timesheet, in there you can see what i mean.

thanks

Dale Howard said:
Reza --

The Project Server administrator can add the Actual Work column to the My
Assignments view (Server Settings - Manage Views). Hope this helps.




reza said:
Hi All,

In my task, if we click Import Timesheet, we will go to Import
Timesheet
table, in that table there were Current Progress.....can we add that
colom
to
My Task. With that colom i can view how many work and total work that
he/she
do [5h of 16h (31%).
anybody know how to add this colom to My Task view???

thanks in advance

reza
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Similar Threads


Top