D
David Luper
We want to keep completed projects from appearing on the timesheets.
We are running a large program (>750 resources, 90 projects (40-50 active at
any one time), and we are in the second phase now. This will be a multi-year
program, and we do not want old projects from appearing.
Normally, this would not be a problem as the Current Tasks view should
filter the completed plans out. However, for about 20-30% of the users, the
Current Tasks filter does not seem to work. We switch back and forth between
All Tasks and Current Tasks, but the user's timesheet does not change.
Thanks!
We are running a large program (>750 resources, 90 projects (40-50 active at
any one time), and we are in the second phase now. This will be a multi-year
program, and we do not want old projects from appearing.
Normally, this would not be a problem as the Current Tasks view should
filter the completed plans out. However, for about 20-30% of the users, the
Current Tasks filter does not seem to work. We switch back and forth between
All Tasks and Current Tasks, but the user's timesheet does not change.
Thanks!