Current Tasks - Project Server 2007

R

Rachel

I have defined a current task as 10 days. However, future assignments are
showing up in resource's My Task page. Any idea why?

Thanks,
Rachel
 
B

Ben Howard

Hi Rachel,
Click on the settings within the My Tasks page, and make sure the check-box
to only show current tasks is selected. This way, only tasks due to start
within the next 10 days, or those that are completed and started 10 days ago,
or those that have started but are not yet complete are shown.
 
R

Rachel

Ben,

Where is the check box on the My Tasks page? I don't see it as an option.

Thanks,
Rachel
 
R

Rachel

Ben,

I just noticed that if I click on the My Work link and look at the My Tasks
page, then I have the option to click the Show Only Current Tasks link.
However, if I go directly to the My Tasks page the Settings pick list is not
there. Any suggestions as to how I can get the Settings pick list to show up
on the My Task page?

Thanks,
Rachel
 
G

Gary L. Chefetz

Rachel:

In the My Tasks page, on the toolbar above the grid, on the right-hand side
next to the view pick list, you should see a menu selection for "Settings."
Use this pick list to show the View Options pane above the toolbar. Be sure
to check the box for "show on menu" the first time you use the Settings
menu.

--
----------
Gary L. Chefetz, MVP
MSProjectExperts
Project Server Consulting: http://www.msprojectexperts.com
Project Server Training: http://www.projectservertraining.com
Project Server FAQS: http://www.projectserverexperts.com
Project Server Help Blog: http://www.projectserverhelp.com
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top